External cladding continues on all townhouses despite wet weather disrupting production throughout July.
Internal and external lock-ups are now complete. Plumbing, electrical, heating and cooling rough-ins are also complete with internal plaster underway in a number of townhouses. This will continue in August. Stairs and kitchen installs to follow after the plaster installation.