Martha Cove Construction Update – February 2017

If you happened to get down to Martha Cove over the summer break, you would definitely have noticed there has been a lot of activity around the area.

STAGE 5:

Edgepoint Homes are working towards a goal of having all properties locked up within the next month.

Half of stage 5 homes will be nearing completion in the next couple of months, and we then expect completion of this stage to be delivered around Sept 2017 (weather dependent).

STAGE 4:

All slabs are on track to be completed on every property within stage 4 by the end of February, with frames to be erected shortly after.

Construction on these homes will be completed by the end of 2017.