Harbourside Terraces Construction Update – November 2015

Stage 1
All timber frames are now complete, with roofs being installed on the majority of the unit blocks.
External lock up, render and external painting has begun and progressing well across the stage and plaster and carpenter fix plus joinery install has commenced.
The last retaining wall works will commence today and once this concludes, along with remaining pits and testing, civils will be finished on this stage.
Stage 2
Floor slabs have been poured to the majority of lots in the stage with structural steel and timber framing now underway.

Stage 3
Electrical, gas and water are now finished on Stage 3 and a perishable layer of rock has been laid on the roadway, ready for underslab drains and concrete slabs to be poured either side of Christmas.

Stages 4 & 5 
Earthworks have begun and are underway, with excess fill being carted off site. Sewer works will begin after Christmas.

Stay tuned for more exciting progress at Harbourside Terraces!

Three Pillars and Edgepoint Homes will be closed this holiday period from the 24rd of December through to the 10th of January inclusive