Harbourside Terraces Construction Update – January 2016

Stage 1
Retaining wall work on Stage 1 is now complete and the rest of Stages 1, 2 & 3 have been handed over from Base Civils to Edgepoint Homes while the build progresses.
All roofs are now completed and the external cladding, render and external painting is progressing to all units. Plaster and carpenter fix to all north units are now complete and joinery has been installed to half of the units. Tiling and painting have commenced.
Stage 2
All floor slabs are poured, structural steel completed and timber framing is well advanced. Roofs have been laid to half the units with services rough ins progressing. External cladding has commenced.Stage 3
South East Water approval has allowed for the commencement of works on Stage 3.
Construction is due to commence this coming Monday, 1st February.

Stages 4 & 5 
Earthworks are 95% complete on Stages 4 & 5 and sewer works are approximately 75% complete. Drainage should be starting in February.

Civil work on the asphalt roads are due to start in the coming months.

We hope everyone had a safe and happy New Year and we look forward to updating you on construction at Harbourside Terraces every two months in 2016.