Harbourside Construction Update – May 2015

Both Harbourside and Harbourside Terraces have seen some great progress lately! Our construction team continues to handover more Harbourside homes, and our civils team has been busy putting in the ground work at the Terraces.

Harbourside

Only a small number of lots are in the slab and framing stages. Roofs are completed at a few other lots, and they are heading into the lock-up stage and painting stage. Twelve lots are nearing completion and two more lots have started hand over.

 

Harbourside Terraces

Trying weather conditions have not stopped our civils team from forging ahead. Drainage is completed at Stage 1 and 2, with electrical and telephone trenching underway now. Road completion is expected in the coming months, and once this is finalised, Stage 3 will be underway.

Visit the Harbourside Terraces Facebook page to keep up to date with everything happening on site and around the Martha Cove Marina!