Central Ave Construction Update – January 2016

Despite Melbourne’s unpredictable weather patterns, the team at Central Ave have been hard at work over the past two months!

The concrete roadways on Lithgow Way and English Close are complete. The brick paving area along Primary Street will have its base poured and the pavers installed by early February. Concrete footpaths around the lower level of the site are being done in stages and street signage will be installed in the coming week.

Stage 2
Units 1-7 are painted and tiled with electrical and plumbing fittings being installed.
Units 12-19, 28-40 are complete on the inside (except carpet and appliances) with landscaping started.
At units 20-21, painting is nearly complete with tilers starting early February.
Units 41-47 are painted and tiled with electrical and plumbing fittings being installed.

Stage 3
At units 48-50, frames are under construction and units 51-57 are ready for painting.
Units 58-62 are ready for plaster, at units 63-69 concrete slabs are being poured and units 70-75 are approaching plastering stage.

We hope you all had a safe and happy New Year and we look forward to updating you on construction at Central Ave every two months in 2016.