St Arnaud Construction Update – September 2017

Overall, construction is progressing well and looking really good!

Internally, all townhouses are now plastered with stairs and kitchens installed. Painting and tiling have now commenced and will continue into mid-October with electrical, heating and plumbing fit offs to follow directly thereafter.

Externally, brickwork to the ground floor has commenced, which when complete will allow the remainder of the external render to be finalised.