St Arnaud Construction Update – May 2017

The progress on Alma road continues this month, with frames nearing completion.

As of the end of April, frames on the front building are 50% complete. Frames and window installation to be completed in May with roofing commenced. Plumbing, electrical, heating & cooling rough-ins and internal lock up to commence thereafter.

Frames on the rear building are now complete, with all windows installed. Roofing will be installed this month. Plumbing, electrical, heating & cooling rough-ins and internal lock up to commence thereafter.